Barrow Offshore Wind Farm
Lua error in Module:Infobox at line 235: malformed pattern (missing ']'). The Barrow Offshore Wind Farm is a 30 turbine 90MW capacity offshore wind farm in the East Irish Sea approximately 7 kilometres (4.3 mi) south west of Walney Island, near Barrow-in-Furness, Cumbria, England.
Construction of the wind farm took place between 2005 and 2006. The farm is operated by Barrow Offshore Wind Limited, owned by Dong Energy.
Contents
Planning and design
Barrow wind farm was a UK Round 1 wind farm development originally developed by Warwick Energy Limited.[1] A planning application was submitted in 2001,[2] and planning consent given in March 2003;[3] the project was sold to Centrica (25%, c.£22.5million), Dong Energy (37.5%), and Statkraft (37.5%) in Sep. 2003.[4][5] The estimated cost of developing the project was £100million, of which £10million was provided by a UK government grant.[5][6] In 2004 Centrica and Dong Energy bought the Statkraft stake, forming a 50:50 joint venture in the development.[7]
The initial Warwick Energy proposal was for a 30 turbine wind farm 7 km southwest of Walney Island (Cumbria), with a generating capacity of up to 108MW; electrical power supply to the mainland was to be via a ~25 km long 132kV cable making groundfall near Heysham, with connection to the mainland electrical grid at an extension to an existing electricity substation south of Heysham nuclear power station.[8] Turbines were expected to have ~50m radius blades, with a 75m hub height, and be situated in water at a depth of ~20m, with a ~32.5m sub-sea bed monopile foundation; the turbines were to be spaced approximately 500m apart in four rows aligned to face the prevailing southwestery winds, with a row spacing of ~750m.[9]
Construction

In July 2004 Kellogg Brown & Root Ltd and Vestas-Celtic Wind Technology Ltd were awarded the contract to install and commission the wind farm, and to operate the wind farm for 5 years.[10] A 30 turbine wind farm with a capacity of 90MW was constructed by the consortium between July 2005 and May 2006. The main construction base was at Harland and Wolff's shipyard in Belfast.[11] In exceptions where pile driving of monopile foundations failed drilling was used to form the monopile foundations.[11][12]
IEC 1A class Vestas V90-3.0MW wind turbines were used, mounted on a 75m tower connected to 4.75 m (15.6 ft) monopiles supplied by a Sif/Smulders joint venture.[13] Turbine to offshore substation electric connection were at 33kV, with the voltage stepped up to 132kV at an offshore substation supplied by Areva T&D (transformer), Sif/Smulders (superstructure and monopile) and designed by KBR and Mott MacDonald. Cables were supplied by Prysmian (33kV) and Nexans (132kV).[14]
Construction of the wind farm was completed in June 2006 with the first power generated in March 2006.[15] The operator is Barrow Offshore Wind Limited, owned by Centrica and Dong.[1]
Operation
Since 2008 (to 2012) the farm operated at between 30 and 40% capacity factor, generating between 240 and 320 GWh of electrical energy per year.[16]
In 2011 regulatory changes required Dong/Centrica to divest the electrical transmission assets of the wind farm, which were sold to TC Barrow OFTO Ltd. for £34 million.[17]
In 2014 Dong Energy acquired Centrica's 50% holding in the wind farm.[18]
See also
- Ormonde Wind Farm, Walney Wind Farm, West of Duddon Sands Wind Farm – other nearby wind farms in the Irish Sea
- List of offshore wind farms in the United Kingdom
- List of tallest buildings and structures in Barrow-in-Furness
References
<templatestyles src="Reflist/styles.css" />
Cite error: Invalid <references>
tag; parameter "group" is allowed only.
<references />
, or <references group="..." />
Sources
- Lua error in package.lua at line 80: module 'strict' not found.
- Lua error in package.lua at line 80: module 'strict' not found.
- Lua error in package.lua at line 80: module 'strict' not found.
- Lua error in package.lua at line 80: module 'strict' not found.
- Lua error in package.lua at line 80: module 'strict' not found.
External links
![]() |
Wikimedia Commons has media related to Barrow Offshore Wind. |
- Lua error in package.lua at line 80: module 'strict' not found.
- ↑ 1.0 1.1 Barrow (4C Offshore) Developers/Owners/Operators
- ↑ Barrow Offshore Wind Farm (LORC) Timeline & Track Records
- ↑ Lua error in package.lua at line 80: module 'strict' not found.
- ↑ Lua error in package.lua at line 80: module 'strict' not found.
- ↑ 5.0 5.1 Lua error in package.lua at line 80: module 'strict' not found.
- ↑ Lua error in package.lua at line 80: module 'strict' not found.
- ↑ Lua error in package.lua at line 80: module 'strict' not found.
- ↑ Barrow wind farm (Non technical summary) (Warwick Energy) pp.1–2
- ↑ Barrow wind farm (Non technical summary) (Warwick Energy) pp.2–3
- ↑ Lua error in package.lua at line 80: module 'strict' not found.
- ↑ 11.0 11.1 Lua error in package.lua at line 80: module 'strict' not found.
- ↑ Lua error in package.lua at line 80: module 'strict' not found.
- ↑ Barrow Offshore Wind Farm (LORC) Turbine, Tower & Substructure
- ↑ Barrow Offshore Wind Farm (LORC) Substations, Inter-Array & Export Cables
- ↑ Barrow Offshore Wind Farm (Dong)
- ↑ Barrow Offshore Wind Farm (LORC) Production and Performance
- ↑ Lua error in package.lua at line 80: module 'strict' not found.
- ↑ Lua error in package.lua at line 80: module 'strict' not found.
- Pages with reference errors
- EngvarB from May 2014
- Use dmy dates from May 2014
- Commons category link is locally defined
- Offshore wind farms in the Irish Sea
- Wind farms in England
- DONG Energy wind farms
- Buildings and structures in Cumbria
- Buildings and structures in Barrow-in-Furness
- Round 1 offshore wind farms
- Power stations in North West England